Project Objective

The purpose of this project is to develop an advanced complex that combines administrative and commercial functions, addressing the needs of modern businesses and efficient office spaces. The “Saba Eight” project also focuses on creating infrastructure that, alongside visual aesthetics, ensures energy optimization and reduction of operational costs

Project Description

1. Design and Implementation of the Steel Structure:

The building’s steel structure was designed and executed using bolts and nuts, making it resistant to earthquakes and compliant with Iran’s national standards. Execution phases included cutting, welding, and assembling metal components, all carried out with high precision in specialized workshops. The use of reinforced concrete shear walls in the design has further enhanced the building’s structural strength.

2. Construction of Retaining and Shear Walls:

Retaining and shear walls were carefully constructed to reinforce the building’s stability against lateral forces (such as earthquakes). These walls play a key role in maintaining structural integrity and reducing the impact of stress on other parts of the building.

3. Composite Roof:

To reduce the building’s weight and boost performance, the roofs were designed and constructed as composite systems. By combining concrete and steel, this type of roof offers an optimal balance of strength and lightness. During implementation, particular attention was paid to precise formwork and concrete pouring

Location

Tehran

Project Specifications

26,000 square meters (14 floors)

b

Project Client

Saba Naft Engineering & Construction Company

Supervising Authority

Sharestan Consulting Engineers Company

Project Duration & Timeline

18 months

Project Start Date

August 2011

تاریخ اتمام

June 2014